None of this could have been achieved without our lovely builders:

Mark, Mike, Sid, Al and Fred

Tuesday, April 7, 2009

Thursday-Monday, 2-6 April 2009

The wallpaper arrived in stock on Thursday and Petros was able to finish papering the two bedrooms on Friday. He also finished painting the loft which is now looking good and ready for us to start moving things over.

On Saturday Paul and Neil carried the washing machine and tumble dryer over to install in the utility room after all the pipework was fixed. Tracy painted the store room (ta duck!) and it now looks clean and fresh, ready for when the freezer is delivered on Thursday.

On Sunday Paul fixed all the base units in the utility and also hung the wall units. We can't get the worktop fitted until next week but at least we now have some storage we can use. Molly (5) bought some violas for Nanny and Grandad's garden and helped her mummy plant them.

I've continued cleaning windows, frames and doors (nearly finished now) and also cleaned up the pleated blinds to go back in the sun room.

On Monday Petros returned and put the first coat of emulsion in both bedrooms and painted more skirtings and architraves. Paul and I, with the help of one of our friends, started to move some of our belongings from our current loft into the new loft at Westbroke. Most of our things will be stored in the loft until the rest of the rooms are finished.