On Friday Mike was doing some plumbing work in the main bathroom ready for the toilet and the bath. Al and Mike continued with the plastering of the staircase, landing and the second bedroom.
First floor landing going towards the loft.
First floor landing looking towards airing cupboard and bedroom:
New wall in second bedroom which had to be studded and plasterboarded due to poor condition of wall caused by past water ingress.
Fred continued with the painting in the loft and managed to complete the third undercoat of emulsion on the walls, plus the ceiling, of the en-suite, together with making a start on the stairway to the loft.