Today didn't have the best start for Mark and the army. Mark arrived with Sid, Al and Fred and immediately had a phone call from Mike asking to be rescued as the van, with a lot of the tools they needed today, had broken down. After unloading the timber and plasterboard they brought with them in the trailer, Mark raced off to see what could be done to get the van going again only to be warned by the police for speeding along the estuary road. He must have had some luck today as he didn't get a speeding ticket!
Just as Mark returned with Mike and the van, temporarily repaired, the delivery of new doors and tiles for the en-suite arrived, although only 11 of the 16 boxes were on the delivery.
Work today consisted of radiators being fitted in the loft bedroom and en-suite, the last of the plasterboarding to the ceiling in the main bedroom was fixed and Fred started stripping wallpaper from the main bedroom.