None of this could have been achieved without our lovely builders:

Mark, Mike, Sid, Al and Fred

Monday, February 2, 2009

Monday, 2 February 2009

Despite overnight snow and extreme cold, the boys were back at their usual time this morning and were straight up onto the roof to sweep off the snow and start slating the dormer side of the roof.












This was taken late afternoon showing how much has been done today, the plan is to carry on with the walls of the dormer tomorrow providing the weather doesn't get any worse.






Mike has been busy concealing the pipework for the sink in the en-suite:







and he then went outside to alter the stack pipe for the new en-suite WC and the new position for the bathroom WC.